Now to Jamberoo Mountain Road, where contractors have completed piling work at Site 3D, with the capping beam installed last week.

Piling work is now completed on Sites 3B and 3D, with the road resurfacing to be completed once all other works are completed.

The soil nails at sites 3A and 3C will commence shortly. The good news? Assuming no more weather delays, the plan is to re-open the road in June…and that is good news.

On Foxground Road, there is progress on the cage and gabion baskets that will stabilise the road.

The re-opening will be advised shortly. Wallaby Hill Road Preliminary work has started at this site following delays due to contractual issues.